PROJECT: POR93854/180069 SR 303 Major Roadway Repair
OWNER: ODOT – District 4
Major project to raise the roadway 4′ -5′ in order to reduce flooding. The construction area tested anywhere from 60′ – 120′ deep peat deposits and included obstacles with wetlands and protection of endangered species.
SCOPE OF WORK:
- Excavation
- Diversion of Tinkers Creek around construction area utilizing water dams
- Installation and removal of normal lightweight material/surcharge remained in place for 2.5 months
- Lightweight, haydite material installed on final roadway – 11,324 CY
- Wickdrains installed through peat soils to expediate project – 167,594 ft
- Geogrid aggregate mat installed to reduce differential settlement
- Animal crossings installed to protect wildlife
- 87′ x 63′ Elyptical culvert installed at Westbowl
- Guardrails
- Paving