SR 303 MAJOR ROADWAY REPAIR
MAJOR PROJECT TO RAISE ROADWAY 4'-5' TO REDUCE FLOODING.
Construction area tested anywhere from 60′ to 120′ deep peat deposits.
The construction area included obstacles with wetlands and protection of endangered wildlife.
SCOPE OF WORK:
Excavation, diversion of Tinkers Creek around construction area utilizing water dams.
Installation and removal of normal lightweight material/surcharge remained in place for 2.5 months; lightweight haydite, material installed on final roadway – 11,324 CY; wick drains installed through peat soils to expedite project- 167,594 FT; geogrid aggregate mat installed to reduce differential settlement.
Animals crossings installed to protect wildlife. 87′ X 63′ elyptical culvert installed at Westbowl. Guardrails and paving.
![ODOT3](https://i0.wp.com/mcamcontg.com/wp-content/uploads/2021/09/ODOT3.jpg?fit=1512%2C2016&ssl=1)
![ODOT1](https://i0.wp.com/mcamcontg.com/wp-content/uploads/2021/09/ODOT1.jpg?fit=1512%2C2016&ssl=1)
![ODOT8](https://i0.wp.com/mcamcontg.com/wp-content/uploads/2021/09/ODOT8.jpg?fit=852%2C1136&ssl=1)
![ODOT10](https://i0.wp.com/mcamcontg.com/wp-content/uploads/2021/09/ODOT10.jpg?fit=%2C&ssl=1)
![ODOT6](https://i0.wp.com/mcamcontg.com/wp-content/uploads/2021/09/ODOT6.jpg?fit=852%2C1136&ssl=1)
![ODOT5](https://i0.wp.com/mcamcontg.com/wp-content/uploads/2021/09/ODOT5.jpg?fit=1512%2C2016&ssl=1)
![ODOT4](https://i0.wp.com/mcamcontg.com/wp-content/uploads/2021/09/ODOT4.jpg?fit=1512%2C2016&ssl=1)
![ODOT](https://i0.wp.com/mcamcontg.com/wp-content/uploads/2021/08/ODOT.jpg?fit=1512%2C2016&ssl=1)